1.       The department wants to ship 100 units of the product at the beginning of week 6. There are 50...

profiledzibderh

 

1.       The department wants to ship 100 units of the product at the beginning of week 6. There are 50 A’s and 100 B’s on hand. In addition, two receipts of 100 B’s each are due, one at the start of week 4 and the other at the start of week 5. Lead time is two weeks for the end item, and one week each for A and B. Prepare an MRP plan for this product using lot-for-lot ordering. Today is the beginning of week 1. .

 